Construction Scheduling
Assignment 6
Suggested format: Times New Roman 12 points, single spaced, 1” margin all around, APA style
for references
Note: All assignments will be checked for plagiarism using SafeAssign. The similarity index
should not be greater than 35% on the report. You should always provide references at the end.
LEARNING OBJECTIVE:
After successfully completing this assignment, students will be able to:
• Perform Earned Value Analysis
• Estimate the status of the project progress quantitatively
Q1. The following depicts a one-year schedule for a project.
After three months on the job (July 1), the contractor concluded that 20% of Activity F
(Activities A, B, and D are completed) was completed, 80% of Activity C was completed, and
40% of Activity E was completed. The project has cost the contractor a total of $535. For this
project, using earned value concepts determine the schedule variance and the cost variance. State
if the project is over or under budget and if it is ahead of or behind schedule. 40 points
Q2. Please follow the instructions below to update the given Project schedule for Earned
Value Analysis. 60 points
The attached MS Project file contains the relationship between activities, estimated durations,
created resources with the maximum amount of resources available together with their estimated
costs, resources assigned to activities as required. You can do the earned value analysis as you
have all the above-mentioned details in the MS Project file.
The following are the steps to run in MS Project and update the schedule:
1. Start by setting a baseline go to <Project, Set Baseline, choose Baseline, OK>.
You need to set a baseline so that you can compare it with your up-to-date schedule later in the
project. In a baseline information is stored in a snapshot of the project including start dates,
finish dates, durations, costs, and amount of work.
2. The next step is to set a status date go to <Project, Status Date, choose 9/27/2020>.
This is the date in which you are updating project progress, by default it will show actual date,
you should change it accordingly.
3. Following you can update the project by updating the tasks’ progress. On ideal conditions,
activities having a satisfactory progress should have completed the amount of work as planned.
Project should be updated on a weekly basis.
Go to <Project, Update Project, Set 0% – 100% complete>
The Gantt chart will show progress bars on the activities.
4. But you want to introduce some changes to the project assuming that you are delayed on some
tasks. You can update progress for each activity individually or for summary activities. Proceed
as follows:
<On the Gantt chart view, Task, information details> OR double click the particular
activity and under the general tab you can change the completed work value in percentage.
a. Phase 1 task 1: 100% complete
b. Phase 1 task 2: 100% complete
c. Phase 1 task 3: 100% complete
d. Phase 1 task 4: 70% complete
5. Next you want to introduce some changes to the budget:
All the labor and equipment costs have been increased by 20% from the estimated to the actual
costs. <Introduce these changes in the Resource Sheet>. Increase all the standard rate value
by 20% in the resource sheet.
6. You can add now two more columns to the work sheet: Baseline Cost and % Complete.
<Add new Column, baseline cost>
<Add new Column, %complete>
You can proceed now to Earned Value analysis:
7. By using the Reports tool, you can obtain the Earned Value curves or the actual values from
the Visual Reports and from Reports respectively.
Go to <Report, Visual Reports, Earned Value over Time, Weekly, OK>
Go to <Report, cash flow report>
ABOUT EARNED VALUE:
• BCWS (Budgeted Cost of Work Scheduled): Shows how much of the budget should have been spent according to original planned or baseline.
• BCWP (Budgeted Cost of Work Performed): How much of the task’s budget should have been spent, given the actual duration of the task?
• ACWP (Actual Cost of Work Performed): Shows actual costs incurred for work already performed by a resource on a task.
• CV (Cost Variance) = BCWP – ACWP : (-) Over Budget or (+) Under Budget
• SV (Schedule Variance) = BCWP – BCWS: (-) Behind Schedule or (+) Ahead of Schedule
• EAC (Estimated at Completion): Forecast of the total actual costs required to complete the project.
• BAC (Budgeted at Completion): Original cost estimate.
• VAC (Variance At Completion) : Forecasted Cost Variance
Our Unique Features
Custom Papers Means Custom Papers
This is what custom writing means to us: Your essay starts from scratch. Plagiarism is unacceptable. We demand the originality of our academic essay writers and they only deliver authentic and original papers. 100% guaranteed! If your final version is not as expected, we will revise it immediately.
Qualified and Experienced Essay Writers
Our team consists of carefully selected writers with in-depth expertise. Each writer in our team is selected based on their writing skills and experience. Each team member is able to provide plagiarism-free, authentic and high-quality content within a short turnaround time.
Free Unlimited Revisions
If you think we missed something, send your order for a free revision. You have 10 days to submit the order for review after you have received the final document. You can do this yourself after logging into your personal account or by contacting our support.
Prompt Delivery and 100% Assuarance
We understand you. Spending your hard earned money on a writing service is a big deal. It is a big investment and it is difficult to make the decision. That is why we support our claims with guarantees. We want you to be reassured as soon as you place your order. Here are our guarantees: Your deadlines are important to us. When ordering, please note that delivery will take place no later than the expiry date.
100% Originality & Confidentiality
Every paper we write for every order is 100% original. To support this, we would be happy to provide you with a plagiarism analysis report on request.We use several writing tools checks to ensure that all documents you receive are free from plagiarism. Our editors carefully review all quotations in the text. We also promise maximum confidentiality in all of our services.
24/7 Customer Support
We help students, business professionals and job seekers around the world in multiple time zones. We also understand that students often keep crazy schedules. No problem. We are there for you around the clock. If you need help at any time, please contact us. An agent is always available for you.
Try it now!
How it works?
Follow these simple steps to get your paper done
Place your order
Fill in the order form and provide all details of your assignment.
Proceed with the payment
Choose the payment system that suits you most.
Receive the final file
Once your paper is ready, we will email it to you.
Our Services
Our services are second to none. Every time you place an order, you get a personal and original paper of the highest quality.
Essays
While a college paper is the most common order we receive, we want you to understand that we have college writers for virtually everything, including: High school and college essays Papers, book reviews, case studies, lab reports, tests All graduate level projects, including theses and dissertations Admissions and scholarship essays Resumes and CV’s Web content, copywriting, blogs, articles Business writing – reports, marketing material, white papers Research and data collection/analysis of any type.
Admissions
Any Kind of Essay Writing!
Whether you are a high school student struggling with writing five-paragraph essays, an undergraduate management student stressing over a research paper, or a graduate student in the middle of a thesis or dissertation, homeworkmarketpro.com has a writer for you. We can also provide admissions or scholarship essays, a resume or CV, as well as web content or articles. Writing an essay for college admission takes a certain kind of writer. They have to be knowledgeable about your subject and be able to grasp the purpose of the essay.
Reviews
Quality Check and Editing Support
Every paper is subject to a strict editorial and revision process. This is to ensure that your document is complete and accurate and that all of your instructions have been followed carefully including creating reference lists in the formats APA, Harvard, MLA, Chicago / Turabian.
Reviews
Prices and Discounts
We are happy to say that we offer some of the most competitive prices in this industry. Since many of our customers are students, job seekers and small entrepreneurs, we know that money is a problem. Therefore, you will find better prices with us compared to writing services of this calibre.